
Platform Holly/Piers 421/Venoco Bankruptcy
Current Status
Plug and abandonment work on Platform Holly resumed in October 2021—528 days after the pandemic shut down this work. As an important milestone, well 3242-6 became the first well plugged to surface. Since then, nine of the 30 wells have been sealed and installed with surface plugs. Operations are now proceeding in a phased approach. Six of the remaining 21 wells require a more involved abandonment procedure. Those wells have been prepared for final abandonment operations. Once these wells are plugged and abandoned, preparation work will begin on the next batch of wells. Staff anticipates that all 30 wells will be plugged and abandoned by the end of the year. Staff also continues to maintain and monitor Platform Holly and the onshore facilities to ensure public health and safety.
Background
In April 2017, Venoco quitclaimed its interests in the South Ellwood Field leases, including Platform Holly and the Ellwood Beach pier leases near the City of Goleta. The quitclaims ended commercial oil and gas production in state waters in the Santa Barbara Channel and returned operational control of these assets to the Commission. California’s Coastal Sanctuary Act prohibits the Commission from issuing new offshore oil and gas leases.
The Commission selected Beacon West Energy Group, LLC as its contractor to operate and maintain Platform Holly and the Ellwood Onshore Facility. Beacon West, under the Commission’s oversight, began ensuring the security and safe daily operations and maintenance at Platform Holly and the Ellwood Onshore Facility in September 2017.
ExxonMobil, the successor in interest to the prior operator, Mobil Oil Corporation, and Venoco’s predecessor for these lease interests, agreed to fulfill its obligation to abandon the 30 wells on Platform Holly, seven of which were Venoco re-drilled wells and are state obligations, and the two near-shore wells on what was Oil & Gas Lease 421 in Goleta (Piers 421 wells).
The Piers 421 wells were successfully plugged and abandoned in 2019. Plug and abandonment work on Platform Holly began in October 2019, only to be halted in March 2020 due to the Covid-19 pandemic and related physical distancing requirements. The Commission maintained 24-hour staffing at Platform Holly and the Ellwood Onshore Facility during the hiatus to ensure health and safety, given the dangerous amounts of hydrogen sulfide gas that is present in the wells until they are fully plugged and abandoned.
Efforts to resume plug and abandonment work on Platform Holly are underway and active well work is expected to resume on September 30, 2021. Plug and abandonment operations are anticipated to continue through completion in early 2023, assuming there are no additional unanticipated delays.
In June 2021, the Commission issued a Notice of Preparation to decommission the PRC 421 wells. The Commission held public scoping meetings later that month and is now preparing an Environmental Impact Report. Piers 421 decommissioning work is anticipated to begin in Spring/Summer of 2022.
Regarding Platform Holly decommissioning, the Commission plans to hire an environmental consultant in mid-2022 to conduct CEQA review. We anticipate that the CEQA process for Platform Holly decommissioning will start in late-2022 and involve robust public and stakeholder outreach. The CEQA process will inform the ultimate decommissioning plan for Platform Holly, which will require Commission review and approval at a public meeting.
Public Meetings & Town Halls
- Public Hearings 02/10/2022
2 p.m. meeting | 6 p.m. meeting - Goleta Town Hall Meeting 12/08/2021
Presentation | Video of the meeting - Public Scoping Meetings 06/24/2021
2 p.m. meeting | 6 p.m. meeting - Goleta Town Hall Meeting 03/10/2021
Presentation | Video of the meeting - Goleta Town Hall Meeting 08/27/2020
Presentation | Video of the meeting - Goleta Town Hall Meeting 11/07/2019
Presentation | Webcast - Goleta Town Hall Meeting 06/27/2019
Presentation | Webcast - Goleta Town Hall Meeting 11/15/2018
Presentation | Video of the meeting - Goleta Town Hall Meeting 05/14/2018
Presentation - Goleta Town Hall Meeting 06/15/2017
Presentation | Photo Gallery
Previous Staff Reports
- 02/27/2018 (92) – Consider delegating authority to the Executive Officer to enter into Agreements necessary for access and operations on former State Oil and Gas Lease Nos. PRC 1466.1, PRC 145.1, and PRC 410.1 related to Rincon Island; and provide an update on the status of Oil and Gas Decommissioning Projects undertaken by the Commission, including the Becker Well Abandonment and Remediation Project and the decommissioning of facilities on former leases encompassing Platform Holly and Rincon Island, off Santa Barbara and Ventura Counties.
- 07/11/1997 (76) – Consider Approval of the Assignment of Undivided Interests in Oil and Gas Lease Nos. PRC 421.1, PRC 3120.1 and PRC 3242.1, and industrial leases PRC 3904.1 and PRC 5515.1, Santa Barbara County
Additional Information
- Final Abandonment of PRC 421-2 Well
- Update on Abandoned Offshore Oil & Gas Wells
- Memorandum of Understanding – CSLC / City of Goleta
- 421 Decommissioning Agreement – CSLC / Exxon
- Phase 1 Agreement – CSLC / Exxon
- Beacon West Energy Group, LLC contract
- ExxonMobil letter of intent
- Reimbursement Agreement extension request
- Request for payment to Aspen Insurance
- Default letter to Venoco
- Reimbursement Agreement
- Resolution
- Assignment Agreement – Mobil Oil Corp. agrees to retain responsibility for the Leases
- Geologic Energy Management Division Orders
- Goleta Oil Release
- Davis v. State of California
Leases, Amendments & Quitclaims
Lease PRC 421 – 10/22/1949
PRC 421 Amendment – 10/22/1959
PRC 421 Amendment – 04/01/1993
PRC 421 Amendment – 08/01/1997
PRC 421 Amendment – 08/26/2013
PRC 421 Quitclaim – 04/13/2017