Offshore Decommissioning

View of Platform Holly from the water on a partly cloudy day with a hill in the background.

Platform Holly

On January 22, staff released a Notice of Preparation to prepare a draft Environmental Impact Report for the Platform Holly Decommissioning Project. On February 19, staff held two hybrid (in-person and via Zoom) scoping meetings to receive public comment on the Notice of Preparation. The public comment period closed on March 6, 2026. 

Learn more
Drone view of Rincon Island and the Causeway.

Rincon Island

On November 7, 2025, the Commission, as lead agency under the California Environmental Quality Act, adopted an Addendum to the Final EIR for the Rincon Phase 2 Decommissioning Project (Certified on August 29, 2024). The Commission also authorized staff to solicit for contractors to implement the Rincon Decommissioning Project.

Learn more