Mineral Resources Management Division — Belmont Island Decommissioning Project
| Removal of Island Structure Begins, May 2000 | |
| Conductors (oil well pipes) were cut by abrasive jet cutting tool 5' below ocean floor and were removed using hydraulic pulling unit. | |
|
Abrasive Jet Cutting Tool |
Hydraulic Pulling Unit (HPU) |
November 2000 |
|
| Removal of fill material inside caisson using conveyor system. | |
|
Conveyor System |
|