Mineral Resources Management Division — Belmont Island Decommissioning Project

Removal of Island Structure Begins, May 2000
 
Conductors (oil well pipes) were cut by abrasive jet cutting tool 5' below ocean floor and were removed using hydraulic pulling unit.

Photo of Abrasive Cutting Tool

Abrasive Jet Cutting Tool
(click photo to enlarge)

Photo of Hydraulic Pulling Unit

Hydraulic Pulling Unit (HPU)
(click photo to enlarge)

November 2000
Removal of fill material inside caisson using conveyor system.

Photo of Conveyor System

Conveyor System
(click photo to enlarge)

 